  TELIBONG AND TELIPOK PROJECTS, SABAH
 
Puncak Niaga Holdings Berhad’s (“PNHB”) scope of works, involving the design and construction of a Water Treatment Plant (“WTP”), intake, off-river storage, two reservoirs and pipe laying, was satisfactorily completed on 31 October 2008 and handed over to Jabatan Air Sabah (JAS) on 1 November 2008 for operation. The 24-month Defects Liability Period and the two years of maintenance work at the WTP undertaken by Puncak Niaga (M) Sdn Bhd (“PNSB”) expired on 31 October 2010 with a list of minor defects, which were rectified in March 2011. Upon the success of the final inspection of the defects, PNHB will apply for a Certificate of Making Good Defects. The WTP treats and supplies 80 million litres of treated water per day to residential developments, industrial parks and tourist resorts in the Tuaran area.  

 

     