MAJOR PROJECTS UNDERTAKEN

A. PRIVATISATION CUM CONCESSION AGREEMENT (PCCA)

View of Draw-off Towers at Langat Dam, source of water to Sg. Langat WTP

PNSB is the holder of two concessions awarded by the State Government of Selangor. The first, a Privatisation Cum Concession Agreement (PCCA) awarded on 22 September 1994, allowed PNSB to take over, operate, maintain, manage, rehabilitate and refurbish 27 existing water treatment plants (WTPs) formerly under the management of the Selangor Waterworks Department. The total production capacity for 27 WTPs is 907 MLD.

PNSB is responsible for the production of treated water up to the quality and quantity designated in its agreement with the State Government of Selangor. Thereafter, the Selangor Waterworks Department manages the distribution of treated water to consumers in the State of Selangor and the Federal Territory of Kuala Lumpur.

The concession expire on 31 December 2020.

 
B. CONSTRUCTION CUM OPERATION AGREEMENT (CCOA)
Washwater Recovery Tanks & Sludge Pumphouse, Sg. Selangor Phase 2
View of Raw Water Pump of Sg. Selangor Phase 2
The second concession, a Construction Cum Operation Agreement (CCOA) was awarded on 22 March 1995 to finance, design, construct, operate, manage and maintain a new 950 MLD WTP at Bukit Badong under the State Government’s Sg. Selangor Water Supply Scheme Phase 2 Project (SSP2). This mammoth project cost RM1.2 billion and was developed in two (2) stages.
 
B(i). SG. SELANGOR WATER SUPPLY SCHEME PHASE 2
Heart of Sg. Selangor Phase 2 Treatment Process – Actiflo Settling Plant
Surge Vessel for the Treated Water Pumping System
The Stage 1 of the Project with a capacity of 475 MLD was commissioned in July 1998, five (5) months ahead of its original schedule during the height of the water crisis that hit Selangor and Kuala Lumpur. The Stage 2 of the Works for another 475 MLD was completed on 31 December 2000 – one year ahead of original schedule.

The concession expire on 31 December 2020.

 
C. DEVELOPMENT AND OPERATION OF WANGSA MAJU WTP
Aerator at Wangsa Maju WTP

In 1998 water crisis, PNSB was also awarded by the Federal Government to develop the Wangsa Maju WTP (45 MLD) on a turnkey basis. The project was successfully completed within a record period of six (6) months on a ‘fast-track’ basis in order to resolve water shortage problem in Wangsa Maju and AU3/Hulu Kelang areas.

Located at Wangsa Maju, this WTP with a design capacity of 45 MLD obtains raw water for treatment from the Klang Gates Dam and Sungai Gombak. The treated water is pumped from the WTP to Wangsa Maju Reservoir and the AU3 Reservoir for distribution.

PNSB has been operating and managing the WTP since its completion in July 1998.

 
D. TURNKEY DEVELOPMENT OF THE DISTRIBUTION SUPPLY
SYSTEM 1 (DSS 1)
Package 2-1C – Over Crossing Pipe (1,700 mm dia.) at Kota Damansara
Starter Board Panel at Batu Estate Pumping Station Pumping Station at Batu Estate
PNSB was awarded by the State Government of Selangor the Distribution Supply System 1 (DSS1) turnkey construction contract sum of RM 317 million. This contract includes the laying of some 75.8km of large diameter pipeline ranging from 1,100 mm to 2,200 mm diameter and construction of three (3) reservoirs with a total capacity of 87 ML and two (2) pumphouses. This project enables treated water from Sg. Selangor WTP to be distributed to consumers in Kuala Lumpur, Gombak, Petaling Jaya and Shah Alam. Works for this contract have been fully completed and commissioned on 12 December 2000.
 
E. DEVELOPMENT OF DISTRIBUTION SUPPLY SYSTEM 2 (DSS 2)
23 ML Bukit Mayong Reservoir Under Construction
Pipe Jacking Work for 2,100 mm diameter at Jalan Sg. Buloh
PNSB has also been awarded by the State Government of Selangor the Distribution Supply System 2 (DSS2) project on a turnkey deferred payment basis which will enable the supply of treated water from Sg. Selangor Phase 2 Scheme to demand areas in Klang and Northern part of Kuala Lumpur. This project includes the laying of some 60.7km of large diameter pipelines ranging from 900 mm to 2,200 mm diameter and construction of four (4) reservoirs with a total capacity of 128 ML. It also includes a pumping system with a capacity of 285 MLD.

The contract value of DSS2 project is about RM 293 million.

The project was practical completed on 08 July 2001.

 
FUTURE PROJECTS
Water demand has a direct correlation with the economic and population growth of the country due to its nature as a basic necessity. 

The Klang Valley still remains one of the key economic areas in the country. Although the population growth in Kuala Lumpur will slow down as the area stablises and becomes fully developed, the regional growth continues at an increasing rate due to the rapid development along the Klang Valley and the new areas of Sepang and Putra Jaya.

The Company will continue to expand and consolidate existing markets while aggressively pursuing new markets. To ensure even greater growth and profitability, we are forging new partnerships and strategic alliances within the industry which will create stronger synergies, reduce costs, and improve performance and profitability. We will continue to concentrate on our core business in the water supply industry, which comprises construction and operation of water treatment plant and water distribution system, while at the same time developing downstream and related business activities.

 
PUNCAK NIAGA HOLDINGS BHD
--Search PNHB
-
-
 

> Pelancaran Briged Penyelamat Sungai Ke-20
> Signing Ceremony between Puncak Research & DHI, Denmark
> Majlis Perhimpunan Sambutan Maal Hijrah Peringkat Kebangsaan 1428H/227M


> Puncak Niaga e-Community is about giving you privileges and listening to you - your suggestion, feedback and enquiry. It's about providing you with Guestbook, Feedback, Frequently Asked Questions and Newsletter. To find out more >>>

 

- You are visitor no 855337                            This site is best viewed at 800 x 600 resolution                          Last updated: Nov 13,2008 -
Copyright © 2008 Puncak Niaga (M) Sdn. Bhd. All rights reserved.