Contract Value (exclude 6% GST)

RM432.6m

Principal Sub-Contractor

Puncak Niaga Construction Sdn Bhd

Duration

5 March 2018 - 19 February 2022 (47 months)

Revised Completion Date (EOT No. 1)

13 June 2022

Scope of Works

• Construction of Central Sewage Treatment Plant (CSTP) of 200,000 PE Capacity

• Construction of 8 Nos Network Pumping Station

• Sewer Pipe Network (66 km)

• Rationalisation and Decommissioning of 100 Public STP and 65 Private STP on Government Premises