Contract Value (exclude 6% GST)
RM432.6m
Principal Sub-Contractor
Puncak Niaga Construction Sdn Bhd
Duration
5 March 2018 - 19 February 2022 (47 months)
Revised Completion Date (EOT No. 1)
13 June 2022
Scope of Works
• Construction of Central Sewage Treatment Plant (CSTP) of 200,000 PE Capacity
• Construction of 8 Nos Network Pumping Station
• Sewer Pipe Network (66 km)
• Rationalisation and Decommissioning of 100 Public STP and 65 Private STP on Government Premises